Question

Would anybody explain how you are using Job Tracker to track the total number of square feet that you are fabricating in your shop each day? (Assuming you complete the fabrication of at least part of one job each day but also leave a portion of some job incomplete each day)

Answer

You can track square feet by job phase using a job form field instead of a job custom field.

By entering the sq. ft. on a form instead of a job custom field, you can have separate forms and sq. ft. values for each phase.

Here’s more information on Job Forms - [|]Creating Job Forms

Here’s more information on Job Phases - [|]Using Job Phases

When you add a form field for Sq. Ft. be sure to use the data type of Number so that you’ll be able to total it on the calendar and in reports.